1. What
is the Productivity rate expressed in Work Hours per LF
(WHR/LF)?
A. 0.57 Work Hours per Lineal Ft.
B. 0.80 Work Hours per Lineal Ft.
C. 1.25 Work Hours per Lineal Ft.
D. 56.00 Work Hours per Lineal Ft.
2. Using
the crew and production information given above what is
the total labor cost for the day?
A. $428.00
B. $532.00
C. $740.00
D. $1,120.00
3. Which
document will help the owner/owner's representative in
assembling a list of responsible builders for bidding on
a project?
A. Addenda
B. Pre-bid Meeting Minutes
C. Pre-Qualification Data
D. Request for Proposals
4. Which
one of the following activities would you consider for
compressing the project schedule:
A. Least Cost Activities
B. Critical Activities
C. Long durationActivities
D. Maximum Float Activities
5. Given
the thickness of reinforced concrete slab is 5", what
is the maximum size aggregate to be used?
A. 1/2"
B. 3/4"
C. 1"
D. 1 1/2"
|