Certification Recognition & Benefits Meet the Professional Constructor Maintaining your Professional Designation Constructor Recognition Survey

Associate Constructor (AC) Questions

Answer the first two questions using the following information.

The plans call for the contractor to install 36 inch Diameter, Class 3, Reinforced Concrete Culvert Pipe with gaskets for the Sewer System.

The Crew consists of:
1 - Labor Foreman
4 - Laborers
1 - Crane Operator
1 - Oiler

Labor Rate and production are:
Labor Foreman - $14.50/hr
Laborer - $13.00/hr
Crane Operator - $16.00/hr
Oiler - $10.00/hr
25 ton Hyd. Crne - $360.00/day
Daily Output - 70 Lineal Ft. (LF)/per 8-hour day

1. What is the Productivity rate expressed in Work Hours per LF (WHR/LF)?

A. 0.57 Work Hours per Lineal Ft.
B. 0.80 Work Hours per Lineal Ft.
C. 1.25 Work Hours per Lineal Ft.
D. 56.00 Work Hours per Lineal Ft.

2. Using the crew and production information given above what is the total labor cost for the day?

A. $428.00
B. $532.00
C. $740.00
D. $1,120.00

3. Which document will help the owner/owner's representative in assembling a list of responsible builders for bidding on a project?

A. Addenda
B. Pre-bid Meeting Minutes
C. Pre-Qualification Data
D. Request for Proposals

4. Which one of the following activities would you consider for compressing the project schedule:

A. Least Cost Activities
B. Critical Activities
C. Long durationActivities
D. Maximum Float Activities

5. Given the thickness of reinforced concrete slab is 5", what is the maximum size aggregate to be used?

A. 1/2"
B. 3/4"
C. 1"
D. 1 1/2"


717 princess street, alexandria, va 22314 | phone: 703.683.5053 | email
© 1999-2003 AICCCC